Bromfield Estates Ludlow

Key Details

  • Project Date: Winter 2024/ Spring 2024

  • Installation of Earth nests around new substations and associated Earthing as per earthing studies and design.

  • Testing of Earthing.

  • Installation of nearly 1000 metres of 11kv 3core cable.

  • Terminations of 11kv cable.

  • Testing & Commissioning.

  • S.A.P. Duties for Energisation with National Grid.

EDS Continental Delivers High Voltage Expertise at Bromfield Estates, Ludlow

EDS Continental’s High Voltage Utility Services (HVUS) team successfully completed a comprehensive project at Bromfield Estates in Ludlow. This project highlights their expertise in high voltage electrical installations and commissioning.

Benefits Delivered:

By successfully completing this project, EDS Continental has equipped Bromfield Estates with a robust and reliable high voltage electrical infrastructure. This translates to:

  • Enhanced safety for occupants and personnel on the estate.
  • Improved power quality and stability for businesses operating within Bromfield Estates.
  • Reduced risk of downtime or power outages.

This project exemplifies EDS Continental’s commitment to delivering high-quality, comprehensive high voltage solutions for their clients. Their expertise ensures efficient project execution and a safe, reliable electrical network.